1997


31st March
Deadline for tenders.
Projects submitted by the following:

  • Carena spa impresa di costruzioni - Genova - joint venture
  • Consorzio cooperative costruzioni - Bologna - joint venture
  • Ferrovial S.A.-Madrid (Spain) - joint venture
  • Impregilo spa - Sesto San Giovanni (Milan) - joint venture
  • Mabetex Project engineering S.A. - Lugano (Switzerland)
  • Philipp Holzmann Bauaktiengesellschaft sud - Munich (Germany) - joint venture

3rd April
Judging Panel appointed to examine tenders, made up of:

  • Leopoldo Mazzarolli, Professor of Administrative Law, University of Padua.
  • Francesco Dal Co, Lecturer in Architectural History, Institute of Architecture, University of Venice.
  • Angelo Di Tommaso, Professor of Building Science, University of Bologna.
  • Ernesto Bottanini fecia Di Cossato, Professor of Technical Plant, University of Padua.
  • Daniel Commins, Director of Acoustic Studies, Architectural Institute of Paris-Belleville and Nancy.

30th May
Judging Panel submits final ranking to Commissioner for Reconstruction:

Impregilo Points 70,1
Holzmann Points 67,5
Carena Points 62,9
consorzio cooperative Points 47,9
Mabetex Points 10,7

31st May
Contract awarded by decree to Impregilo spa, representing a joint venture between the following:

FIAT Engineering spa
SACAIM spa
COVECO
ICCEM srl

5th June
Conference called to approve the project.

6th June
Project approved with ruling of Commissioner for Reconstruction.
Appointment of Chief Engineer and Works Manager, respectively Felice Setaro and Roberto Scibilia.

27th June
Contract drawn up (File N. 6).
Contract value: Lit. 90,202,168,686 including reduction.
Contract deadline: 823 consecutive days (from assignment of contract).

27th June
Work opened
Work to be completed: 27/09/99.

30th June
"Survey Committee" appointed:
prof. Achille Chiappetti
prof. Giuseppe Creazza
prof. Mauro Strada.

Philipp Holzmann and Carena appeal against the judging procedure to the Regional Administrative Court of the Veneto.

9th October
Both appeals are rejected. Rulings 1480/97 and 1497/97.
The two parties appeal against the rulings to the Council of State.

back   next

 

Reconstruction work

Images

collegamento alle immagini

Timeline

Work programme

Programma dei lavori

Project staff

Architect
Director of works
Contractor

 
Logo del Commissario Delegato per la Ricostruzione




HELP rebuild La Fenice Theatre




italian