From
the 1996 fire to the present day
2002
25th January
Contract drawn up with S.A.C.A.I.M. (File Nº 14).
Contract value: Euro 52,959,425.42
28th January
S.A.C.A.I.M. delivers executive project.
5th March
Commission for the Preservation of Venice approves external modifications.
Completion of survey of executive project by Works Management and Proceedings Manager.
7th March
Advisory Committee set up by Commissioner for Reconstruction approves executive project.
8th March
Commissioner for Reconstruction approves executive project, with increase in remuneration of Euro 1,867,548.57.
10th March
Foundation work begun by Dolomiti Rocce completed.
11th March
Foundation work delivered early.
Reconstruction work assigned urgently to S.A.C.A.I.M.
Deadline: 630 consecutive days.
Work to be completed: 30/11/03.
5th April
Amendment to S.A.C.A.I.M. contract drawn up.
Contract value: Euro 54,826,973.99
26th March
1st Certificate of payment of advance to the value of Euro 2,741,348.70
2nd Certificate of payment of advance in accordance with Article 16, Subparagraph 1 of contract to the value of Euro 1,027,749.23.
19th July
Order by Commissioner for Reconstruction N° 203/UCD/AMM appointing technical, administrative and static survey committee.
26th July
3rd Certificate of payment for 1st Progress Stage in accordance with Article 30 of the Special Tender Specification.
26th September
1st interim production deadline, 200 days from assignment of works in accordance with Article 13, Subparagraph 2. Site survey is positive.
21st October
Works Manager issues survey order for amendment at no extra cost.
11th November
Director of Works issues approval (N° 482/RUP) for amendment survey.
2nd December
4th Certificate of payment for 2nd Progress Stage in accordance with Article 30 of the Special Tender Specification.
6th December 1st conformity document issued for the first amendment survey.
back next
|